An upgraded version of Orbital ATK’s commercially developed Antares rocket has at last rolled out to its launch pad on the Virginia shore – thus paving the path for a high stakes first stage engine test looming “in the next few weeks,” according to the aerospace firm.
“This stage test paradigm is a design verification test, said Kurt Eberly, Orbital ATK Antares deputy program manager, in an interview with Universe Today.
The rocket will be erected at the pad during the full power hot fire test which is scheduled to last approximately 30 seconds. Hold down restraints will keep the rocket firmly anchored at the pad.
“After the 30 second test is done we will shut it down and have a pile of data to look at,” Eberly told Universe Today.
“Hopefully it will confirm all our environments and all our models and give us the confidence so we can proceed with the return to flight.”
Indeed the significance of the hot fire engine test cannot be overstated because the entire future of Antares as a viable launch vehicle and resuming delivery of NASA cargo to the International Space Station (ISS) depends on a successful outcome of the crucial test firing – following a devastating launch failure 19 months ago.
Orbital ATK hopes to restart resupply missions to the crews living aboard the space station as soon as July – less than two months from today.
The now revamped launch vehicle dubbed Antares 230 has been re-engined and upgraded with a pair of modern new first stage engines, the Russian-built RD-181 fueled by LOX/kerosene.
To prepare for the upcoming stage test, workers carefully assembled and thoroughly tested an Antares first stage equipped with the new RD-181 engines.
On May 12, 2016, they moved the vehicle on a dedicated multi-wheeled transporter from the Horizontal Integration Facility at NASA’s Wallops Flight Facility to Virginia Space’s Mid-Atlantic Regional Spaceport Pad-0A about a mile away.
The team has about 3 weeks of check out work to complete before the live firing, including a wet dress rehearsal (WDR).
“The team will continue to work meticulously as they begin final integration and check outs on the pad and several readiness reviews prior to the test. The window for the stage test will be over multiple days to ensure technical and weather conditions are acceptable,” noted Orbital ATK in a statement.
The ‘Return to Flight’ blastoff – currently planned for as soon as July 2016 – will be the first for the private Antares rocket since a catastrophic launch failure on Oct. 28, 2014, just seconds after liftoff from Wallops. That flight was carrying Orbital ATK’s Cygnus cargo freighter on the critical Orb-3 resupply mission for NASA to the space station.
The launch mishap was traced to a failure in the AJ26 first stage engine turbopump and caused Antares launches to immediately grind to a halt.
Top Orbital ATK management soon decided to ditch the AJ26s, which were 40 year old refurbished engines, originally built during the Soviet era and originally known as the NK-33.
They sought a replacement and eventually decided to upgrade Antares by powering it with a pair of new Russian-made RD-181 main stage engines and modifying the first stage core structure to accommodate the new engines.
The RD-181 flight engines are built by Energomash in Russia.
“They are a good drop in replacement for the AJ26. And they offer 13% higher thrust compared to the AJ26,” Eberly noted.
As a result of switching to the new RD-181 engines, the first stage also had to be modified to incorporate new thrust adapter structures, actuators, and propellant feed lines between the engines and core stage structure.
Independent review teams have also been brought in to ensure that no stone is left unturned and everything is being done to achieve success.
Now it’s time for the real deal. After all the hard work Antares is now at the pad.
“We place it on the pad about 3 weeks prior to the engine test,” Eberly told me. “Then we and do a series of integrated checks, and electrical checks and pressure checks on the feed lines.”
“Then we will do a wet dress rehearsal where we will load the tanks with propellants. We will load the pressure bottles, pressurize the tanks and then count down just like we would for the real stage test. And right before we ignite the engines we will call a halt to the sequencer.”
“Then we will detank and pick through all that data and do a readiness review.”
If the WDR goes well, the full up engine test will follow.
“Then we will do the stage test,” Eberly explained.
“It is a 30 second test. We will fire up both engines and hit all 3 power levels that we plan to use in flight.”
“We will use the thrust vector controls. So we will move the nozzles and sweep them through sinusoidal sweeps at different frequencies and excite various resonances and look for any adverse interaction between fluid modes and structural modes.”
The vehicle and pad will be outfitted with lots of special instrumentation to gather as much test data as possible.
“We will have a lot of accelerometers and extra instrumentation and extra microphones on the test article and around the pad.
“After the 30 second test is done we will shut it down and have a pile of data to look at.”
“That will hopefully confirm all our environments and all our models and give us the confidence so we can proceed with the return to flight on the OA-5 mission.”
The test uses the first stage core planned to launch the OA-7 mission late this year.
After the engine test is completed, the stage will be rolled back to the HIF and a new stage fully integrated with the Cygnus will be rolled out to the pad for the OA-5 ‘Return to Flight’ mission as soon as July.
In the past 6 months, Orbital ATK has successfully resumed launches of their Cygnus cargo freighters to the ISS – as an interim measure until Antares is returned to flight status
They utilized the United Launch Alliance (ULA) Atlas V rocket to deliver two Cygnus resupply vessels to the ISS on the OA-4 flight in Dec. 2015 and OA-6 flight in March 2016.
Stay tuned here for Ken’s continuing Earth and Planetary science and human spaceflight news.
Sometimes in science you have to step back and take another look at underlying assumptions.…
For the past thirty years, NASA's Great Observatories - the Hubble, Spitzer, Compton, and Chandra…
Thanks to Hubble, JWST, and the Planck mission, we're starting to see cracks in the…
One of the great things about CubeSat designs is that they constrain the engineers who…
China's growing presence in space has been undeniable since the turn of the century. Between…
When Oumuamua traversed our Solar System in 2017 it was the first confirmed Interstellar Object…